Continued with storm sewer installation.
·
Site
clean-up prior to July 4th Weekend.
Work Anticipated to be Performed, July 3rd to
July 7th
·
No work scheduled to be performed on Monday,
July 3rd or Tuesday, July 4th on-site
·
Complete needed storm sewer repairs and cleaning
within existing storm sewer system.
As
stated in previous posts, since this project is funded by the Village of
Glenview, construction will not be delayed due to the current shut-down of IDOT
projects.
Have a
safe and enjoyable July 4th Weekend.