Installed topsoil and erosion blanket within
ditch lines.
Work Anticipated to be Performed, July 31st to
August 4th
·
Complete needed storm repairs within existing
system that were identified during televising inspection.
·
Remove existing pavement
·
Perform excavation and installation of gravel
base in areas of pavement widening
The contractor installed
topsoil with a straw erosion control blanket within the ditch lines and in
areas where construction previously occurred. No grass seed was installed under
the straw blanket. The contractor will lay sod during the September/October
timeframe when growing conditions are more favorable. The straw erosion control
blanket was installed to prevent the topsoil from eroding away and entering the
storm sewer system during rain events.
Thanks again for all your
patience as the project continues.