Friday, August 25, 2017

Asphalt Paving Completed

Work Performed, August 21st to August 25th    
·         Paved final surface layer of asphalt
·         Performed final testing of water main system

Work to be Performed
·         Asphalt driveway restoration
·         Minor repairs indentified outside the pavement
·         Final inspection with Village staff prior to project close-out.
·         Sod Restoration, to be performed in mid-September when growing conditions are typically more favorable.

Friday, August 18, 2017

Final Layer of Asphalt Surface Pavement Being Scheduled

Work Performed, August 14th to 18th   
·         Started final testing of water main
·         Made repairs to water main identified during testing
·         Adjust manholes prior to final grade
·         Internally televising underground storm sewers
·         General site clean-up.

Work Anticipated to be Performed, August 21st to August 25th  
·         Complete final testing of water main
·         Pave final layer of asphalt

The contractor will continue to install and grade topsoil; however, sod will not be installed until mid-September when the growing conditions are typically more favorable.

Hopefully a majority of the construction work, with the exception of sod installation, will be completed in the next 1-2 weeks.

Thanks again for all your patience and understanding.

Monday, August 14, 2017

Preparing for Asphalt Paving

Work Performed, July 31st to August 11th  
·         Completed final storm repairs within existing system that were identified during televising inspection.
·         Removed existing asphalt pavement surface
·         Pavement widening and patching as required
·         Excavated and installed base for driveway access to 811 / 801 Becker Road
·         Paved first layer of asphalt for driveway access to 811 / 801 Becker Road
·         Prepared for asphalt driveway restorations
·         Reinstalled mailboxes

Work Anticipated to be Performed, August 14th to August 18th .
·         Adjust manholes prior to final paving
·         Perform internal televising of sewers.

The contractor will be working to performing several miscellaneous tasks prior to paving the final layer of asphalt including all final testing of the underground work performed.

The asphalt driveways will be restored following the installation of the surface layer of asphalt.

Hopefully a majority of the construction work, with the exception of sod installation, will be completed in the next 2-3 weeks.

Thanks again for all your patience and understanding.