Monday, August 14, 2017

Preparing for Asphalt Paving

Work Performed, July 31st to August 11th  
·         Completed final storm repairs within existing system that were identified during televising inspection.
·         Removed existing asphalt pavement surface
·         Pavement widening and patching as required
·         Excavated and installed base for driveway access to 811 / 801 Becker Road
·         Paved first layer of asphalt for driveway access to 811 / 801 Becker Road
·         Prepared for asphalt driveway restorations
·         Reinstalled mailboxes

Work Anticipated to be Performed, August 14th to August 18th .
·         Adjust manholes prior to final paving
·         Perform internal televising of sewers.

The contractor will be working to performing several miscellaneous tasks prior to paving the final layer of asphalt including all final testing of the underground work performed.

The asphalt driveways will be restored following the installation of the surface layer of asphalt.

Hopefully a majority of the construction work, with the exception of sod installation, will be completed in the next 2-3 weeks.

Thanks again for all your patience and understanding.